Emboreet: Construction and extension of the Secondary School | Geographic position: 3°57’29.25 “S 36°26’31.13 “E |
2021- Construction of a dormitory for girls
- Purchase of beds and mattresses
- Installation of six more water tanks on the school grounds
- Construction of a building with washing and shower cabins
- Construction of a toilet block
- Construction of four classrooms
- Purchase of school benches
- Fencing of the school grounds, among other things, to protect against wild animals
- Handover to the government as operator of the school on December 3, 2021
| 2020- Construction of two dormitories for boys
- Purchase of beds and mattresses
- Construction of wash and toilet houses for boys and girls
- Construction of four residential houses (row houses) for teachers
- Construction of two first-aid rooms for boys and girls
- Construction of two water towers with water tanks for washrooms
- Repair of the solar system (inverter)
- Handover to the government as operator of the school on December 3, 2021
|
2019- Construction of a double dormitory for the “house father” of the students and the “house mother” of the girls
- Construction of a dormitory for girls
- Purchase of beds and mattresses
- Construction of three classrooms
- Purchase of school desks
- Teaching materials and equipment for the laboratories
- Construction of pedestals for water tanks at the washrooms and toilets
- Construction of an incinerator for the girls’ toilets
- Handover to the government as operator of the school on October 19, 2019
| 2018- Connection of the buildings to the solar power supply system
- Construction of a dormitory for girls
- Purchase of beds and mattresses
- Handover to the government as operator of the school on May 12, 2018
- Construction of a computer center and equipment with 21 modern computers
- Construction of a library with bookshelves, tables and chairs for studying
- Handover to the government as operator of the school on October 20, 2018
|
2017- Construction of the science rooms for biology, chemistry and physics
- Handover to the government as operator of the school on September 29, 2017
- Construction of six terraced houses as residential buildings for teachers
- Handover to the government as operator of the school on February 19, 2018
| 2016- Construction of a multipurpose hall with kitchen
- Delivery of 650 modern, simple chairs and 100 tables
- Delivery and installation of a modern audio/video system in the multipurpose hall
- Construction of a steel framework with four water tanks for storage
- Laying of the main supply lines for water in the school premises
- Construction of toilet and washing facilities with connection to the water network
- Construction of three biogas digesters at the toilets
- Connection of the kitchen to the water network and the biogas from the digesters at the toilets
- Construction of a solar plant with batteries for the power supply of the school
- Handover to the government as operator of the school on October 20, 2016
|
2015- Construction of two dormitories for boys
- Purchase of beds and mattresses
- Construction of a double dormitory for teachers and their families
- Handover to the government as operator of the school on November 13, 2015
| 2014- Borehole, water tank and solar groundwater pump.
- Handover to the government as operator of the school on October 16, 2014
|
| |